HARDENING THE GAGES
CPAC action item #15 assigned to Carl Goodwin
February 2000 - Columbia CPAC Meeting
Here's where ICOM stands to date with a gage hardening checklist. Kevin Oberg is consulting with Tom Yorke as to
whether this should be released as an OSW memo. In any case, it probably should still have the review of the
Regional Surface Water Specialists to see if anything should be added. (per Thomas Zembrzuski, 5/11/2000)
Appendix A:
Checklist and Guidance for Hardening Gaging Stations
The checklist is intended to aid districts in evaluating their gaging stations and to serve as
guidelines for consideration when funds are available for gages scheduled to be upgraded.
Floods, natural hazards:
- Are gage instrument shelf locations above the peak stage of the design flood? (NSIP calls for instruments
to be placed above 200-year flood elevation.)
- Are the gage shelter and appurtenances located so as not to be vulnerable to bank erosion, damage from
flood-borne debris, land slides, or falling trees?
- Can the gage shelter be safely accessed at all times and all stages?
Vandalism:
- Does the site have a history of vandalism, or are there telltale signs of potential for vandalism (shot-up signs,
shell casings nearby, party litter, etc.)?
- If so, is the gage shelter appropriately "fortified" to withstand likely level of vandalism? Some options for
consideration are:
- Bullet-proof/fire-proof shelter
- Bullet-proof instrument enclosure
- Steel doors
- Welded steel lock covers/anti-theft lock systems
- Antennas, solar panels protected
- Secured cable cars
- Fencing
- Security alarm systems
- As appropriate, enlist support of local observers who will contact the District and local law enforcement
authorities if they observe vandalism.
- Use Visual Identity signage; include purpose of gage and office telephone number.
- Always report acts of vandalism to local law enforcement authorities.
Redundancy:
Evaluate the need for independent and redundant data streams, and the seriousness of the consequences of a break
in the data stream. Depending on local site conditions, gage shelter vulnerability, and how important an
uninterrupted flow of data is to the District, it.s cooperators, and the general public, a number of actions may
be appropriate.
- Use multiple transmission systems (GOES; radio; microwave; land-line telephone; cellular telephone; satellite
telephone)
- Have portable, temporary gage(s) ready for deployment (available from the HIF)
- Install backup or parallel instruments and sensors
- Install independent gage shelters
- Use uninterruptible power sources
- Arrange for independent or redundant data dissemination by other agency(s) (e.g. Corps of Engineers or National
Weather Service)
- Arrange for observer(s) on call
Construction/instrumentation actions/choices:
- Steel or concrete structures mounted on concrete pads
- Increased reliability of orifice lines to the channel with use of new bubble gages (Design Analysis H-350/H-355
or Sutron Accubble).
- Electrical enclosures used rather than sheet metal
- Equipment inside shelter is secure (structure may vibrate during floods)
- Antenna placed inside the shelter to reduce vandalism and wind damage
- Pressure sensing lines underground
- Sound building practices used, such as using pressure treated lumber, galvanized nails, etc.
- Surge suppressors for protecting electronic and telecommunications equipment from lightning and line current
spikes
- Proper grounding of electronic equipment
Click on a major heading to other links!
TOP #top
CPAC home /cpac/
CPAC Columbia Minutes /cpac/minutes/000225_sc_minutes.html
Search //wwwqvarsa.er.usgs.gov/search.html
Address questions or comments to Charles Merk, CPAC Secretary
cfmerk on (703) 648-5680