USGS
Internal USGS Access Only

 

The Development of a USGS, WRD
Computer Hardware and Software
Inventory System (CHASIS)

Introduction

As the USGS, WRD, moves into a new era of computing wherein non-DG Unix servers and NTs will begin to take over many of the Division’s important computing roles and responsibilities, there is a great need for a set of enterprise-wide inventorying and management tools. The rapid changes taking place in the WRD computing environment have made tasks such as hardware and software support and management a difficult set of tasks. Previously, when such efforts could be defined and managed for a nearly uniform computing environment (as was the case under the Distribute Information System-II (DIS-II) contract) defining management and support was a more straightforward task. The determination and allocation of support, maintenance, and management resources needed for a heterogeneous computing environment is a daunting task made more difficult by the fact that there are insufficient data available about the mix of hardware and software throughout the Division. Furthermore, as the year 2000 approaches, there is an increasing realization that the Division must have in place an inventory database of both hardware and software so that informed estimations may be made about the possible adverse consequences of the year 2000 (Y2K) bug. The development of a computer inventory tool for systems, applications, and licensing will provide WRD with a starting component for a much needed set of enterprise-wide management tools.

 

Purpose and Scope

During fiscal year 1998, the Distributed Information System (DIS) Program Office and the Mississippi District began discussions about the development of a computer inventory database for the USGS, WRD. The need for such an inventory was brought before the USGS, WRD, Computer Policy Advisory Committee (CPAC) by Gloria Stiltner, Chief DIS Program Office. CPAC recommended the effort for funding during their meeting of November 17-19, 1998, that was held at the Miami Subdistrict office. Subsequently, funding was allocated and preliminary arrangements have been made to begin development of the Computer Hardware and Software Inventory System (CHASIS). The minutes of the CPAC meeting may be found at the following URL:

http://wwwqvarsa.er.usgs.gov/cpac/mins/981117.miami.html

The purpose of the funded effort is the development of a CHASIS. The development of CHASIS will have several major components. There will be a server side which will comprise the data from all individual sites, and there will be client application which will be used to accumulate the relevant data for each WRD site. The client database application will be developed using Microsoft Access, the database included in WRD’s supported desktop productivity suite, Microsoft Office, Professional Edition. The application will include a series of database tables for tabulating information about WRD office sites and hardware and software in use at each site. The client application will provide customized data entry forms for all data tables and will provide system administrators (SAs) with the ability to easily add, modify, and delete data for their site. The client application will be distributed to SAs. Each District will maintain a local database which will be replicated to a central site where aggregation will occur, analysis will be conducted, and data and reporting services will be provided. Types of data that will be tabulated in the table will include specifics about hardware configurations, operating systems, licensed software (such as GIS software), specialized network hardware, and Y2K compliance status.

Prior to the release/distribution of the database application to all District and Sub-District offices, the database will be preloaded on the server with the information generated during the "Baseline Data Compilation" phase of the workplan. The Baseline Data Compilation will include compiling data from DIS contract purchases that can be retrieved from the DIS database, acquiring all names of machines that have registered IPs (through Jim Fisher of the Office of Program Support - OPS), and pulling together the data from Graig McHendrie's original data set (and new database for Lotus). Additional data to be preloaded includes license information for ESRI, SAS, S-Plus, and Frame, as well as other new data such as LAN and WAN equipment where deemed necessary. Further data will be tabulated as to the use of MSOffice, Ingres, and other licensed or corporate (NWIS, AIS, Travel Manager, etc.) software on specific equipment. Each equipment item or tabular record will be referenced to a site by the use of a "site code" database item. The site code will likewise be an item in a spatial database as a point attribute item that will allow all tables to be linked to a spatial database, accessed, and served to the USGS Intranet in a map-based form through a web-enabled GIS application.

The database application will be distributed to all Districts and Sub-Districts with preloaded information included. The local database will be maintained by the local computer section staff and will be populated by using customized forms. Each WRD district will have a "site" file that will be used to provide information about the spatial location of the office and will provide primary keys for other tables to use for links. There will be separate tables for hardware items, software items, maintenance items, and license tracking if needed (or desired). The site code will serve as the primary key - foreign key link item between tables. All sites will maintain their local database. Provision will be made so that individual program offices (such as the Geographic Information Programs Office - GIPO) may maintain the data for which they are responsible.

Data that has been populated from each site will be aggregated at a central server site. From the central server site the database will be made generally available to the WRD Intranet through custom web client interfaces that will include both a map-based interface and general query forms. Direct connection to the database for aggregate, break-out, and drill-down analysis, and resource management will be provided to the Office of Information, DIS, CPAC, and other groups as necessary. A Windows NT Terminal Server will be purchased and configured with database, programming, and all necessary software and hardware to develop, store, and serve the aggregate database. The hardware and software configured to develop, store, and serve CHASIS will remain in the Mississippi District as District property and will be maintained by District personnel.

 

Objectives

CHASIS will be designed, developed, tested, implemented, populated, and put on the WRD Intranet prior to October 1, 1999. The delivered application will primarily consist of a designed database, preloaded data, electronic database input forms, and methods for data aggregation, analysis, and web serving. Specific functional items that the database will provide include:

 

Client Application Items

 

Server Application Items

 

Intranet Client Application

  

Workplan

As proposed, the development of CHASIS will be conducted in the following stages and will be completed per the included timelines.

Task Component

Time to Complete

Projected Start

Projected Completion

System and Database Design 1 1/2 months February 1, 1999 March 15, 1999
Client & Server Application Development 1 1/2 months March 15, 1999 May 1, 1999
Identification of Baseline Data Sources 1 month February 1, 1999 March 1, 1999
Baseline Data Compilation 1 month March 1, 1999 April 5, 1999
Preload Database 1 month April 5, 1999 May 3, 1999
Identify Test Sites 1 week May 3, 1999 May 10, 1999
Preliminary Client & Server Design Test 1 week May 10, 1999 May 17.1999
Pre-acceptance Testing 3 weeks May 17, 1999 June 7, 1999
Application and Database
Modifications
2 weeks June 7, 1999 June 21, 1999
Final Testing and Modifications 2 weeks June 21, 1999 July 6, 1999
User Notes and Release Notes 1 month May 3, 1999 June 7, 1999
Distribution of Client
Application
1 week July 6, 1999 July 12, 1999
Installation Support 2 weeks July 12, 1999 July 26, 1999
Site Data Compilation 2 weeks July 26, 1999 August 9, 1999
Data Aggregation 2 weeks August 9, 1999 August 23, 1999
Data & Server Application Publication 3 weeks August 23, 1999 September 20, 1999

 

Design

The database and application design will be accomplished using visual programming rapid application development (RAD) tools included in Microsoft Visual Studio 6. The database design and data dictionary will be developed and reviewed prior to implementation. Application development will be coordinated such that there will be preliminary, beta, and final testing and acceptance phases. Version control software will be used to ensure the controlled development of the database and related applications. The database and application will be designed to provide an inventory mechanism sufficient for current and future expected information needs. Preliminary requirements have been stated by the DIS Program Office and for Y2K compliance issues. A complete list of design requirements will be generated and maintained on a "to be developed" web site that will also include design documentation for the database and all related client- and server-side applications.

 

Personnel and Resources

Personnel, hardware, and software resources needed to design, develop, and implement CHASIS are currently available within the Mississippi District. A team approach will be followed in developing and implementing CHASIS. The team members will be available over the time-line of the project, and their estimated time for the project life-span is included in the following table:

Person

Role

Status

Time

Susan Trapanese Project Leader HQ, SSU Chief  
Chuck O’Hara Team Leader and Design Leader MS District, GIS
Specialist
2 Months
Sridhar Katragadda Database Design Leader MS District, Contract Employee 6 Months
Gail Kalen Baseline Data Compilation Testing Leader MS District, System Administrator 2 Months
Darius Mott Database Developer MS District, Student 4 Months
Scott Dennis Web Design Leader MS District, Web Master 2 Months

 

Currently, it is estimated that 25% of the funding will go toward Sridhar’s contract, 25% will go toward student costs, and the remaining 50% will be allocated toward the server, storage, and software to be used in developing and serving the database. A server has been identified and tested as has an advanced disk storage system for the aggregate database and applications.